Publicity of exposure draft of environmental impact report of cleaner production and transformation project of concrete admixture series products of Sichuan TongZhou Chemical Technology Co., Ltd

Publicity of exposure draft of environmental impact report of cleaner production and transformation project of concrete admixture series products of Sichuan TongZhou Chemical Technology Co., Ltd

  • Categories:News
  • Author:
  • Origin:
  • Time of issue:2019-12-26
  • Views:71

(Summary description)According to the relevant requirements of the regulations on the administration of environmental protection of construction projects and the classified management directory of environmental impact assessment of construction projects issued by the Ministry of environmental protection, Sichuan TongZhou Chemical Technology Co., Ltd. has carried out the environmental impact assessment of the cleaner production transformation project of concrete admixture series products. Now the draft of the project environmental impact report has been prepared, Publicize it according to the measures for public participation in environmental impact assessment and other relevant provisions, and solicit opinions related to the environmental impact of the construction project:

Publicity of exposure draft of environmental impact report of cleaner production and transformation project of concrete admixture series products of Sichuan TongZhou Chemical Technology Co., Ltd

(Summary description)According to the relevant requirements of the regulations on the administration of environmental protection of construction projects and the classified management directory of environmental impact assessment of construction projects issued by the Ministry of environmental protection, Sichuan TongZhou Chemical Technology Co., Ltd. has carried out the environmental impact assessment of the cleaner production transformation project of concrete admixture series products. Now the draft of the project environmental impact report has been prepared, Publicize it according to the measures for public participation in environmental impact assessment and other relevant provisions, and solicit opinions related to the environmental impact of the construction project:

  • Categories:News
  • Author:
  • Origin:
  • Time of issue:2019-12-26
  • Views:71
Information

In accordance with the relevant requirements of the Regulations on the Management of Environmental Protection of Construction Projects and the Ministry of Environmental Protection's Catalogue for the Classification and Management of Environmental Impact Assessment of Construction Projects, Sichuan Tongzhou Chemical Technology Co., Ltd. has carried out the environmental impact assessment of the clean production transformation project of concrete admixture series products. Work, the draft of the project environmental impact report has been prepared, and it will be publicized in accordance with the "Measures for Public Participation in Environmental Impact Assessment" and other relevant regulations to solicit opinions related to the environmental impact of this construction project:

I. Overview of the environmental impact report of the construction project

1. Construction project situation

Project Name: Cleaner Production Transformation Project of Concrete Admixture Series Products

Construction owner: Sichuan Tongzhou Chemical Technology Co., Ltd.

Construction nature: renovation and expansion

Construction content: More than 30 sets (sets) of equipment such as 10-square reaction kettle, neutralization tank and automatic production control system are newly added. After the renovation of the project, 60000t/a of polycarboxylate superplasticizer, 4000t/a of concrete pumping agent (water agent), 1000t/a of concrete pumping agent (powder), 2000t/a of concrete expansion agent and 20000t/a of accelerator , mortar admixture (water) 3000t/a, mortar admixture (powder) 500t/a, foaming agent (water) 5000t

/a, the production capacity of conditioner (powder) 500t/a, activator (water agent) 1000t/a, polypropylene engineering fiber 200t/a (only for sub-packaging but not for production).

2. Status Quo of Regional Environmental Quality

1) Air quality

Inhalable particulate matter (PM10) and fine particulate matter (PM2.5) in the ambient air quality of the project exceed the standard, so the area where the project is located is a non-standard area. The Mianyang Air Quality Compliance Plan within a Time Limit (2017-2020) proposes that the Mianyang air quality compliance strategy mainly includes the following contents: First, it focuses on the pollution control of the building materials industry, the comprehensive control of "scattered pollution", and the ultra-low emission transformation of power plants. The second is to deepen the prevention and control of dust source pollution and effectively reduce the emission of dust particles. The fifth is to promote the coordinated control of multi-pollutants for air pollutants such as sulfur dioxide, nitrogen oxides, inhalable particulate matter, fine particulate matter, volatile organic compounds, and ammonia, and to incorporate ammonia emission control into the policy. vision. Through the actual measurement, the characteristic factors meet the standards in the reference limits of air quality concentration of other pollutants in Appendix D of "Technical Guidelines for Environmental Impact Assessment - Atmospheric Environment" (HJ2.2-2018).

2) Water environment quality

According to the "2018 Mianyang Municipal Environmental Status Bulletin", the water quality of the Fujiang River in the evaluation reaches meets the requirements of Category III in the "Surface Water Environmental Quality Standard" (GB3838-2002), and the surface water environment quality of the evaluation reaches is good.

During the monitoring period of regional groundwater, all monitoring indicators of groundwater within the evaluation scope meet the requirements of Category III of the Groundwater Quality Standard (GB/T14848-2017).

3) Sound environment quality

Status monitoring shows that the daytime and nighttime noise monitoring values ​​of each noise monitoring point in the proposed project site meet the Class 3 area standards in the Acoustic Environment Quality Standard (GB3096-2008).

4) Soil environmental quality

According to the monitoring data, the soil environment quality in the area where the project is located meets the second category of land use risk screening value standard of "Soil Environment Quality - Construction Soil Pollution Risk Management and Control Standard (Trial)" (GB36600-2018), and the regional soil environment quality is good.

3. Environmental protection measures and discharge standards

1) Waste gas treatment measures

The waste gas released from the reactor in the production workshop is collected through the pipeline, and then treated by the waste gas treatment device, and then discharged by a 15m exhaust pipe; the process dust is collected by installing a gas collecting hood above the reactor and the mixing barrel, and then enters a set of bag filter for treatment. The 15m exhaust pipe is discharged; the feeding and stirring dust produced by mortar admixture (powder) and regulator (dust) is collected by installing a gas collecting hood and then entering a set of bag filter for treatment and then discharged through a 15m exhaust pipe; the waste gas in the tank area is discharged through nitrogen The breathing exhaust gas after the sealing device is collected by the pipeline and then processed by the activated carbon adsorption device and then discharged unorganized.

2) Wastewater treatment measures

The pure water to prepare concentrated water, boiler sewage, and circulating cooling water mainly contains low-concentration suspended solids, which belong to clean water and can be directly discharged into the rainwater pipe network.

The newly added laboratory wastewater, waste gas water spray wastewater and initial rainwater will be coagulated and deposited in the existing three-stage sedimentation tank set up in the laboratory and then discharged into the sewage pipe network, and finally discharged into the Tangxun sewage treatment plant for treatment.

3) Noise control measures

The project selects advanced, high-quality, low-noise equipment; basic shock absorption measures are taken for the production equipment, and the workshop adopts sound insulation windows. Anti-vibration and anti-shock measures are taken in the design and selection of support and hanger to reduce the noise generated by vibration. After adopting sound insulation, noise reduction, vibration reduction and other treatment measures for different noise sources, the sound source can be made less than 70dB(A). , to achieve noise emission standards.

4) Solid waste disposal measures

The solid waste generated by the project has been properly disposed of and will not cause secondary pollution to the surrounding environment.

5. Environmental impact analysis

1) Atmospheric environmental impact

Comprehensive environmental impact prediction and analysis, the project waste gas has been properly disposed of, will not change the regional atmospheric environmental function changes. The project will not cause significant impact on the surrounding residents and other environmentally sensitive points.

By setting the delineated sanitary protection distance in this project, the impact of unorganized discharge of the project on the surrounding environment can be solved. At the same time, the project strictly controls the exhaust gas to avoid the impact of the project's unorganized emissions on the surrounding environment to the greatest extent.

2) Water environment impact

The pure water to prepare concentrated water, boiler sewage, and circulating cooling water mainly contains low-concentration suspended solids, which belong to clean water and can be directly discharged into the rainwater pipe network.

New laboratory waste water, waste water spray waste water and initial rainwater will be discharged into The sewage pipe network is finally discharged into the Tangxun Sewage Treatment Plant after reaching the standard treatment and then discharged into the Fujiang River. Therefore, the wastewater of this project will not have a direct impact on the environmental quality of surface water in the area where the project is located.

3) The impact of solid waste on the surrounding environment

The project classifies the generated solid waste, and all kinds of solid waste are recycled or properly disposed of, and will not be discharged outside, resulting in no secondary pollution.

4) Influence of the acoustic environment

Adopt measures such as reasonable layout of the general plane, shock absorption, sound insulation, and noise reduction, etc., and achieve the factory boundary standard after distance attenuation, and will not change the regional acoustic environment function.

6. Key points of environmental impact assessment conclusions

The construction of the project conforms to the national industrial policy, and the construction project has obtained the pre-examination opinion on land use. The land used for the project is industrial land, and the land used is in line with the land use planning of the Mianyang Economic and Technological Development Zone. Opinions” (Chuanhuan Jianhan [2015] No. 176). The site selection of the project is reasonable, the impact of the completion of the project on the local environmental function is small, and the project has good economic and social benefits. According to the pollutants that may be generated during the production process of the project, corresponding control measures have been considered and suggested in this report. As long as the construction unit strengthens management and seriously adopts the pollution prevention and control measures proposed by the EIA, the impact of the project construction on the environment is acceptable. Considering and analyzing from the perspective of environmental impact, the construction of this project is feasible.

2. Public Scope for Solicitation of Comments

The scope of soliciting public opinions is mainly about the opinions of the people around the construction project and social groups (including: village committees, enterprises and institutions, etc.) on the environmental impact of the construction project.

3. Public Opinion Form and Internet Links to the Draft for Comments

Link to public comment form:

https://pan.baidu.com/s/195mdyyMWEabGklZcELY18g Extraction code: a32s.

Links to the Draft for Comments:

https://pan.baidu.com/s/1TWaAHL8Ium_3mN1Vxs512Q Extraction code: qmdg.

4. Ways and channels for public comments

The public can submit the completed public opinion form to the construction unit through letters, faxes, emails and other contact methods, and give feedback on the opinions and suggestions related to the environmental impact of the construction project.

When the public submits comments, please provide valid contact information; it is encouraged to submit comments by real name and provide a resident address. For the relevant personal information submitted by the public, our company promises that it will not be used for purposes other than public participation in environmental impact assessment.

5. The starting and ending time of public comments

Within 10 working days after this announcement is published.

6. Contact information of the construction unit

Unit name: Sichuan Tongzhou Chemical Technology Co., Ltd.

Unit address: No. 169, Tangxun East Road, Economic Development Zone, Mianyang City, Mianyang Economic and Technological Development Zone, Mianyang City

Contact: Mr. Luo

Contact number: 18113403261

Email: 137724199@qq.com

Keyword:

Scan the QR code to read on your phone

Hot news

Publicity before approval 2020-03-14 20:04:00
Sichuan Tongzhou Chemical Technology Co., Ltd. Concrete Admixture Series Products Cleaner Production Transformation Project Environmental Impact Report and Public Counselor's Full Text Publicity (Announcement Before Approval) Sichuan Tongzhou Chemical Technology Co., Ltd. "Concrete Admixture Series Products Cleaner Production Transformation Project" has been After completing the review, the project should be publicized before submitting for approval in accordance with the Measures for Public Participation in Environmental Impact Assessment (Order No. 4 of the Ministry of Ecology and Environment). (1) Name and summary of the construction project Project name: Cleaner production and transformation of concrete admixture series products Project overview: Sichuan Tongzhou Chemical Technology Co., Ltd. Development Park), and implement the clean production transformation project of concrete admixture series products in the existing factory area, which is in line with the planning and industrial positioning of Mianyang Economic and Technological Development Zone in Mianyang City. (2) Name and contact information of the construction unit Construction unit: Sichuan Tongzhou Chemical Technology Co., Ltd. Contact person: Mr. Luo Industrial Development Park of Technology Development Zone) (3) Name of the unit that prepares the environmental impact report Environmental impact assessment unit: Sichuan Jiashengyu Environmental Protection Engineering Co., Ltd. Contact: Wang Gong Room B3-201, Santai Rubik's Cube, No. 42, Shuxi Road, Jinniu District, City (4) The content of the announcement is: "Environmental Impact Report on Cleaner Production Reconstruction Project of Concrete Admixture Products" Instructions for Public Participation in Environmental Impact Assessment of Cleaner Production Transformation Projects for Chemical Products. See Annex 1 and Annex 2 for details. The public can provide comments in the following ways: (1) by E-mail, fax; (2) by telephone directly; (3) by letter. Publicity time: March 14, 2020 ~ March 27, 2020 Publicity before approval: https://pan.baidu.com/s/1Qx_llCN6mmpOdeO7tShskg Extraction code: 8zgx Public participation instructions download: https://pan.baidu. com/s/1f17OB2Fru0pGmEus-ldcRQ Extraction code: m1tx

Service Hotline: 028-84363387
Headquarters address: Room 2305, Times 1, No. 6, Zhiquan Section, Dongda Street, Jinjiang District, Chengdu City, Sichuan Province (Exit A of Dongmen Bridge Station, Metro Line 2)
Factory Address: No.169, Tangxun East Road, Economic Development Zone, Mianyang City, Sichuan Province

Copyright  © 2021 Sichuan Tongzhou Chemical Technology Co., Ltd.  蜀ICP备19008600号-1